OPERATION
COOLDOWN AND STARTUP
Before the Pump is operated, all parts which come in contact with
the cryogenic fluid must be cooled down to the temperature of the
liquid; otherwise, sporadic vaporization will cause erratic pumping
action. Proceed with cooldown as follows:
- CHECK FREE ROTATION OF PUMP BEFORE EVERY COOLDOWN AND STARTUP.
- Close discharge valve and open bypass valve.
- Slowly open the suction valve. At the beginning of cooldown the
liquid in-flow will be subject to fast evaporation. As the Pump
cools down sporadic vaporization will cease, and the suction valve
may be fully opened.
- After a ten (10) minute cooldown, start Pump and open vent
valve. If Pump does not prime in ten (10) seconds, stop motor,
close vent valve, and cool down for another two (2) minutes.
- Repeat step (4) until Pump is primed (discharge pressure is
developed). Close vent valve.
- Slowly open discharge valve while closing bypass valve. If Pump
loses prime, open bypass valve and vent valve momentarily until
discharge pressure is again developed.
- Throttle discharge valve to maintain desire discharge pressure.
Opening the discharge valve excessively may break the suction flow
or overload the driver.
STARTUP AFTER SHORT SHUTDOWN PERIODS
- Open suction valve and vent valve, and crack bypass valve.
- Start the Pump driver.
- When Pump primes, open discharge valve and close vent valve and
bypass valve.
SHUTDOWN
- Stop the Pump driver.
- Close suction, discharge, and bypass valves.
- Crack open vent valve; this will relieve pressure without
drawing atmospheric moisture into the Pump.
Copyright 1998, 1999© Cryogenic
Machinery Corporation. All Rights Reserved.
For problems or questions
with this site contact webmaster@cryomach.com
Web site designed and maintained by
Infinite Loophole Designs
|